The Schedule Performance and
Cost Performance Indices not only monitor current project performance,
they can also be used to predict future performance trends.
To-Complete
Performance Index (TCPI) = (BAC-EV) / (BAC-AC). Indicates
the CPI required throughout the remainder of the project to stay
within the stated budget.
Estimate at
Completion (EAC) = AC + ((BAC-EV)/CPI). A forecast of
total costs that will be accrued by project completion based on past
cost performance trends.
Variance at
Completion (VAC) = EAC – BAC. The difference between the
new Estimate at Completion and the original Budget at Completion.